Pages

Wednesday, April 6, 2016

How to Calculate Earned Value

Planned value - Budgeted cost of work planned called planned value.
Actual cost - Actual cost is the total cost incurred for the actual work completed.
Earned value - Budgeted cost of work performed call earned value.

1. EV = PV to date x RP
    RP = Rate of performance
    
2. Cost variance = EV – AC
    AC = Actual cost

3. Schedule variance = EV – PV
    
4. CPI – Cost performance index
    CPI = EV/AC
    This gives the efficiency of work.

5. SPI = Schedule performance index
    SPI = EV/PV

6. EAC – Estimated actual cost
    EAC = BAC/CPI
    BAC – Budgeted actual cost


7. Actual finishing date of the project = Original period of project / SPI

No comments:

Post a Comment