(Figure 01)
In
many contracts, the owner requires the contractor to provide an S-curve of his
estimated progress and costs across the life of the project. This S-shaped of
the curve results because early in the project, activities are mobilizing and
the expenditure curve is relatively flat. As many other activities come
on-line, the level of expenditures increases and the curve has a steeper middle
section. Toward the end of a project, activities are winding down and
expenditures flatten again (Figure 01). The S-Curve is one of the most commonly
techniques to control the project costs.
An S-curve can be useful as a means
through which control of work can be affected. The minimum necessary
information for this purpose id illustrated in figure 01. The cumulative
budgeted expenditure that is the cost to be incurred by a contractor in
construction is represented by the full-time of S-curve. The actual expenditure
curves show the current cumulative cost at any point in time up until the
present or time now.
The actual expenditure just exceeds the
budgets time now in the figure 01. However, it may or not represent better
progress than that expected. From the figure 01, the conclusion is that over
budget has been incurred than was budgeted at time now. The progress is behind the budget. Cost is expended at a
faster rate than budget and may cause cash flow problems.
Thus, overall attention needs to be paid
to the efficiency of the work methods, productivity and financing. From figure
01, it will be seen that a forecast of expenditure to complete the work shows a
likely final overrun, but will cause delay in completion of the project. The
vertical axis of the S-curve graph is usually expressed in units of money. However,
it is also can be expressed in terms of work content, for example, cubic meters
of excavation, tones of structural steel erected, or man hours of work content
for a particular operation or a group of activities.
For a project with a number of activities,
it is much easier to use an S-curve for each one, to ensure that progress
advances as require. It is practicable and useful to use a scale of
percentages, the whole of the particular work under consideration expressed as
100 percent in addition to using units of work on the vertical scale. These
types of scales obviate the need to change the total quantity of work involved
when variation to it is scope occur.
No comments:
Post a Comment