A number
of different procurement routes and options exist in the construction industry;
1. Traditional
(Design - Bid - Build)
2. Design
and Build
3. Management
Contracting
4. Construction
Management
5. Design
and Manage
Traditional
System -
The traditional structure for project procurement is seen as a sequential
method because the employer takes his scheme to an advanced stage with his
professional team before appointing a contractor. The designer is employed to
advise the client, design and ensure that the work is kept within the budget
and that it complies with the standards required. A Quantity Surveyor can be
engaged to give assistance on design costs and budgets, prepare bills of
quantities, check tenders, prepare interim valuations and advise on the value
of variations.
Advantages
of Traditional System
- Competitive tendering is
possible with detailed documentation
- High quality of functional
standard are possible
- There is cost certainty at
the start of construction
- Independent advice is given
on most aspects of the process
- BoQs make for
ease of valuation of variations and high level of cost control and
monitoring
- There is a flexibility for
design changes in the construction stage
- A combination of the best
design and construction skills is possible
Disadvantages
of Traditional System
- Decision processes are slow
and convoluted
- Total project time is the
longest of all options and no parallel working is possible
- No integration between
design and construction process leads to reduced team spirit & tend to
cause problems at construction stage
- The clients’ liability&
risk is significant – where the client is inexperienced
- Due to time pressure in the
pre contract stage, the documentation may have errors - Cost overruns
Methods in
Traditional System
Lump sum
method means the contractor agrees to build a project with a specific scope for
a fixed price. A lump-sum contract is suitable if the scope and schedule of the
project are sufficiently defined to allow the contractor to fully estimate
project costs.
Cost plus
is a contract agreement wherein the purchaser agrees to pay the cost of the
work, including all trade contractor work, labor, materials, and equipment,
plus an amount for contractor overhead and profit. These types of contracts are
favored where the scope of work is indeterminate or highly uncertain, and the
kinds of labor, material, and equipment needed are also uncertain.
With
cost-reimbursable alternative contracts, contractors are paid for the work with
a mix of reimbursable and fixed or incentive costs. Cost-reimbursable
alternative contracts are effective when the general scope of work and
schedule are defined, but there is uncertainty in quantities or execution.
Under cost-reimbursable alternative contracts, uncertainty in project scope is
borne by the client. Cost-reimbursable alternative contracts offer significant
flexibility for responding to conditions that are uncertain. There are
different variations of basic cost-reimbursable alternative contracts,
including cost-reimbursable plus fixed fee, cost-reimbursable plus
performance-based incentives, direct cost-reimbursable plus fixed
construction management costs, and others.
Unit
price means this kind of contract is based on estimated quantities of items
included in the project and their unit prices. The final price of the project
is dependent on the quantities needed to carry out the work. In general, this
contract is only suitable for projects in which the scope is
reasonably well established, and the different types of items (but not their
numbers) can be accurately identified in the contract documents.
A
guaranteed maximum price (GMP) contract is a cost-type contract, in
which the construction contractor is compensated for actual costs
incurred, plus a fixed fee subject to a ceiling price. The contractor is
responsible for cost overruns, unless the GMP has been increased via formal
change order as a result of additional scope from the client. Savings resulting
from cost under runs are returned to the client.
No comments:
Post a Comment